News
2016.12.05
Daelim Holds Upstream Cofferdam Completion Ceremony for Pakistan’s Gulpur Hydroelectric Power Project

Daelim Holds Upstream Cofferdam Completion Ceremony
for Pakistan’s Gulpur Hydroelectric Power Project
 


The attendees pose for a commemorative photograph in front of the cofferdam.

Daelim held the upstream copper dam completion ceremony at Pakistan’s Gulpur hydroelectric power plant construction site on November 12. The provincial governor, the police agency commissioner, and client’s employees attended the completion ceremony.

 


Site manager Lee Dong-ho talks about his impression of the dam.

Designed to block upstream water, the upstream cofferdam was completed 6 months ahead of the contracted due date thanks to all employees’ efforts. The dam is 31.5m high and 154m long. The remaining construction is expected to be completed by 2019. 